Skip to content
Supreme Court of India (all four decisions)

Fateh Chand v Balkishan Das (1963) to Kailash Nath Associates v DDA (2015)

Say the ratio out loud before you open Reasoning — recalling it unprompted is exactly what the exam pays for.

Why it matters

This is not one case but a chain of four, and the examiner will want the chain rather than any single link. Together they answer the standard fifteen-mark question: "Indian law makes no distinction between liquidated damages and penalty. Discuss."

The English courts spent a century building machinery for sorting an agreed sum into one of two boxes. If it was a genuine pre-estimate of loss it was liquidated damages and recoverable in full; if fixed in terrorem of the promisor it was a penalty and the whole clause was thrown out, leaving the plaintiff to prove his damages at large. The classic statement of the tests is Lord Dunedin's in Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd, 1915 AC 79 (HL) — the tyre maker's £5-per-tyre clause against price-cutting dealers was upheld as liquidated damages because a precise pre-estimate was impossible and £5 was not extravagant.

S. 74 discards that machinery. It puts every stipulated sum — genuine pre-estimate, penalty, forfeiture clause, escalated interest — into one funnel and produces one answer: reasonable compensation not exceeding the amount named. The named sum ceases to be the measure of recovery and becomes only the ceiling.

The four cases work out what that means, and the last of them, Kailash Nath, is the one students get wrong most often.

Facts

Fateh Chand (1963). Balkishan Das agreed in 1949 to sell Fateh Chand a plot of land with a bungalow in Delhi for Rs 1,12,500. The buyer paid Rs 1,000 at the moment of the agreement, described as earnest money. On being put into possession he paid a further Rs 24,000. The contract said that if he did not pay the balance and get the conveyance registered by 1 June 1949, the Rs 25,000 already paid would stand forfeited, the agreement would be cancelled and possession would go back to the seller. The buyer defaulted. The seller forfeited the whole Rs 25,000 and sued for possession and for compensation for the buyer's use and occupation in the meantime.

Maula Bux (1969). A contractor undertook to supply potatoes to the Military Headquarters, U.P. Area, under one contract and poultry, eggs and fish under another. He deposited Rs 10,000 under the first and Rs 8,500 under the second — Rs 18,500 in all — expressly as security for due performance. He supplied irregularly and short. The Government rescinded both contracts and forfeited the whole deposit. It made no attempt at trial to show what the alternative source of supply had cost it.

ONGC v Saw Pipes (2003). ONGC ordered casing pipes from Saw Pipes for an offshore drilling project. Saw Pipes had to source raw material from Europe; a general strike in the European steel mills held up the material and delivery ran late. ONGC granted an extension but expressly reserved the right to recover liquidated damages, and then deducted roughly US $3,04,970 and about Rs 15.75 lakh from the running bills under a clause that fixed damages at a stated rate per week, capped at 10 per cent of the contract value. The arbitral tribunal held that ONGC had led no evidence of financial loss and ordered the deductions refunded. ONGC challenged the award under s. 34 of the Arbitration and Conciliation Act 1996.

Kailash Nath (2015). In 1982 the DDA auctioned Plot No. 2-A at Bhikaji Cama Place, New Delhi. Kailash Nath Associates bid about Rs 3.12 crore; the bid was accepted on 18 February 1982 and 25 per cent — about Rs 78 lakh — was deposited as earnest money, the balance to follow by May 1982. Then the property market collapsed. The DDA, acting on the recommendations of its own high-powered committees, extended time generally for auction purchasers, and in December 1987 wrote asking whether the appellant would pay with 18 per cent interest. The appellant agreed the same day. The DDA then did nothing for years, and on 6 October 1993 — without notice — cancelled the allotment and forfeited the entire Rs 78 lakh. On 23 February 1994 it re-auctioned the same plot for about Rs 11.78 crore.

Issues

  1. Does s. 74 apply only where a party claims a fixed sum, or also where a party seeks to forfeit money already in his hands?
  2. Is money paid as earnest treated differently from a deposit or an advance?
  3. Do the words "whether or not actual damage or loss is proved to have been caused thereby" mean that a claimant under s. 74 need prove nothing at all?

Arguments

The recurring defence of the party holding the money was textual: s. 74 speaks of "a sum … named in the contract as the amount to be paid in case of such breach", so it governs a claim to receive, not a right to retain. In Maula Bux the Union added that Rs 18,500 was a genuine pre-estimate; in Kailash Nath the DDA argued that earnest money stands outside s. 74 altogether and is forfeitable as of right.

The claimants answered that s. 74's second limb — "or if the contract contains any other stipulation by way of penalty" — is deliberately wide, and that a forfeiture clause is functionally identical to a payment clause: the money simply happens already to be on the other side of the table.

Held

Fateh Chand. The seller could keep the Rs 1,000 earnest, but not the Rs 24,000 as a forfeiture. Shah J held that the words "any other stipulation by way of penalty" cover "every covenant involving a penalty whether it is for payment on breach of contract of money or delivery of property in future or for forfeiture of right to money or other property already delivered." Where a deposit is forfeited under such a clause, "the court has jurisdiction to award such sum only as it considers reasonable, but not exceeding the amount specified in the contract as liable to forfeiture." The seller was allowed compensation for the buyer's use and occupation of the bungalow, and the balance was refunded.

Maula Bux. Rs 18,500 was a security deposit, not earnest. The Court refused to treat every advance deposit as earnest, adopting the classical description of earnest as a token sum given to signify assent, and the Privy Council's formula in Chiranjit Singh v Har Swarup that earnest "is part of the purchase price when the transaction goes forward: it is forfeited when the transaction falls through by reason of the fault or failure of the vendee." Since the Government proved no loss at all, it recovered nothing and had to refund the deposit.

ONGC v Saw Pipes. The award was set aside. On s. 74 the Court held that where the contract fixes a genuine pre-estimate by way of liquidated damages and the loss is of a kind that cannot realistically be quantified, the named sum may be awarded as reasonable compensation without separate proof of the amount of loss.

Kailash Nath. The forfeiture was wholly bad. R.F. Nariman J held that there was no breach by the appellant at the relevant time, and that in any event the DDA had suffered no loss whatever — it had resold the plot for nearly four times the original bid.

Ratio

Read the four together and the operative propositions are these.

  1. S. 74 applies to forfeiture clauses as much as to payment clauses, and to a defendant retaining money as much as to a plaintiff claiming it (Fateh Chand; confirmed in Kailash Nath).
  2. The named sum is a ceiling, never a floor. The court awards reasonable compensation up to it.
  3. Reasonable compensation is worked out on ordinary contract principles — that is, by reference to s. 73. S. 74 does not create a free-standing right to money.
  4. Loss or damage caused by the breach is a sine qua non for the application of s. 74 (Kailash Nath, in terms).
  5. The words "whether or not actual damage or loss is proved to have been caused thereby" excuse quantification, not existence. They apply where damage or loss is difficult or impossible to prove; there the named sum, if a genuine pre-estimate, may be taken as the measure.
  6. Forfeiture of a reasonable sum paid as earnest money under a contract of sale does not attract s. 74 at all, because it is not the imposition of a penalty. Forfeiture of a security deposit, an advance towards price, or an unreasonably large "earnest" does attract it.
  7. Kailash Nath adds one qualification: where forfeiture takes place under the terms of a public auction before any agreement is concluded, s. 74 has no application.

Reasoning

Shah J's insight in Fateh Chand is that the English penalty rule is a rule about enforceability of a clause, while s. 74 is a rule about quantum of relief. Under English law the court must swallow the clause whole or spit it out whole; under s. 74 it may take the parties' figure as a starting point and scale it down. As Fateh Chand puts it, s. 74 "is clearly an attempt to eliminate the somewhat elaborate refinements made under the English common law in distinguishing between stipulations providing for payment of liquidated damages and stipulations in the nature of penalty", the Legislature having "sought to cut across the web of rules and presumptions under the English common law by enacting a uniform principle applicable to all stipulations naming the amount to be paid in case of breach and stipulations by way of penalty."

The earnest/deposit distinction survives that flattening because earnest money does a different job. It is part-payment of price given as a token of seriousness; its forfeiture is an incident of the bargain, not a sanction for breach. Once the sum is large, or is expressly held as security for performance rather than appropriated to price, the label stops mattering and the substance — a penalty for breach — takes over. That is exactly the move Maula Bux makes on facts nearly identical to those the High Court had called earnest.

Now the point on which candidates lose marks. ONGC v Saw Pipes did not hold that proof of loss is never necessary. It held something narrower: where the consequences of breach cannot be reduced to a rupee figure — delay to an offshore drilling programme, for instance — the court will not force the innocent party into an impossible arithmetical exercise, and will treat a genuine pre-estimate as the reasonable compensation. Loss was assumed to exist; only its measurement was excused. The wide-sounding sentences must be read against those facts. (ONGC is also famous in arbitration law for a separate reason — it read "patent illegality" into the "public policy of India" ground under s. 34 — and that aspect has since been narrowed by the 2015 amendment to the Arbitration and Conciliation Act and by later decisions.)

Kailash Nath makes explicit what Fateh Chand and Maula Bux assumed. Nariman J's summary states that "damage or loss caused is a sine qua non for the applicability of the section", and that "whether or not actual damage or loss is proved to have been caused thereby" means only that "where damage or loss is difficult or impossible to prove, the liquidated amount named in the contract, if a genuine pre-estimate of damage or loss, can be awarded." On the facts the DDA had gained roughly Rs 8.5 crore on the re-auction. There was nothing to compensate.

What came after

Kailash Nath is now the standard citation for the proposition that s. 74 is compensatory and not punitive. On the burden of proof the settled position is workable rather than tidy: the claimant must show that loss of some kind flowed from the breach, but where quantification is genuinely impracticable and the contractual figure is a bona fide pre-estimate, the court will award it, leaving it to the party in breach to demonstrate that no loss at all was occasioned. Some High Courts had already reasoned this way before 2015 — as in the Jagson International line, where a predetermined amount was upheld because the defaulter led no evidence that the claimant escaped loss.

Two further strands deserve a line each. Chunilal V. Mehta & Sons Ltd v Century Spg & Mfg Co Ltd, AIR 1962 SC 1314 holds that where the contract expressly provides for compensation, the right to claim damages at large under the general law is excluded — the managing agents there were confined to the Rs 6,000 per month the clause gave them. And the Explanation to s. 74 makes a stipulation for increased interest from the date of default a stipulation by way of penalty, so courts routinely scale exorbitant default rates down.

In the app

The analysis continues in the app with Criticism and limitswhere the decision is criticised and how far it reaches and Exam usehow to write this case into an answer, plus every card and question built on this case.

Related cases in this unit

Parts of the judgment

Precedents cited

  • Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd
  • ONGC v Saw Pipes
  • Chiranjit Singh v Har Swarup
  • ONGC v Saw Pipes.
  • Chunilal V. Mehta & Sons Ltd v Century Spg & Mfg Co Ltd